Newsroom

Limit search

Occupational accidents have declined by half in 2017–2021 – electrical accidents have not

Accident statistics collected by electricity distributor Caruna from work sites in its network area have revealed a worrying trend. Although there has been a significant reduction in occupational accidents, electrical accidents are still the most common among electrical professionals, and the number of these accidents has not decreased. Caruna's safety data has now been collected on the seif.fi website, where the causes that led to safety deficiencies, and the conclusions, can be found.
Press release ·

In the first week of October, Caruna will analyse the condition of the electricity network at night in various parts of Espoo

In the first week of October, beginning Monday 4 October, you may see Caruna's vans on the move at night in various parts of Espoo. The vans carry a device that monitors Caruna's low-voltage electricity network and indicates any network faults it detects. Similar studies have previously been conducted in the United States, Canada and various parts of Europe. The technology is now being put to the test in Finland for the first time.
Press release ·

Caruna ready to net small-scale production

The new amendment to the Government Decree allows hourly netting of small-scale production and consumption. This means that Caruna will automatically compensate for production that is not used in a one-hour period in the small-scale producer's distribution invoice.
News ·

Electricity solutions for specific needs: Cultivation with grow lighting in greenhouses uses a lot of electricity for the needs of growing

In Finland, the growing season is naturally short, but by using grow lighting, Finnish crops can be produced year round. Lighting that provides strength to growth is the biggest electricity user in a greenhouse, and annual usage can easily reach tens of thousands of megawatt hours. Electricity for the Juntti market garden will soon be delivered via their own Caruna primary substation
Article ·

Construction of Sinimäki primary substation and related 110 kV underground cable connection begins in Espoo – effects on traffic arrangements

In the next few years, a new substation will be built in Sinimäki to meet the needs of growing electricity consumption and to support Espoo's carbon-neutral strategy. An underground high-voltage cable of six kilometres will also be installed during the project to connect the substations in Leppävaara and Sinimäki.
Press release ·

A carbon-neutral future is the common goal of Espoo and Caruna – cooperation agreement signed

The City of Espoo and electricity distribution company Caruna Espoo Oy signed an agreement on strategic cooperation on March 31, 2021. The aim of the cooperation is to support Espoo's growth and carbon-neutrality targets with a strong electricity network that meets future energy needs, enabling clean energy solutions for Espoo residents and companies.
Press release ·

Primary substation to be built in Sinimäki, Espoo, to meet growing energy demand and improve reliability of electricity distribution in Espoo

Caruna is building a new primary substation in Sinimäki, Espoo, in response to the increasing energy consumption in Espoo as well as to support Espoo's carbon-neutral strategy and leadership in clean energy solutions. An underground cable will be installed during the project to connect the primary substations in Leppävaara and Sinimäki. The main contractor is Destia Oy. The total value of the Sinimäki project is approximately EUR 30 million of which Destia's share is EUR 15 million.