Connection rates
You will receive the right to connect to the electricity network when you sign a connection contract and pay the connection fee.
We use the so-called zone pricing to set the electricity connection rates. A connection zone is determined by the distance to the nearest secondary substation and the size of the main fuse box. The connection fee for new low voltage connections is determined according to the size of the main fuses used on the connection.
The price is based on the average construction costs incurred in expanding the new electricity network in each zone, as well as a capacity reservation fee. The connection fee includes the activation of the connection and installation of the electricity meter.
Further details on how the connection zones are determined are provided below. The prices of electricity connections are shown in the rates at the bottom of this page. Caruna has two network companies, Caruna Oy and Caruna Espoo Oy. Choose the rates according to which network company's territory your plot of land is located in.
Find out the price of your connection on our connection order pathway
Find out the price of your connection on our connection order pathway. If you can't get a price estimate on the pathway, contact our experts via chat. We will confirm the connection price in the connection contract. The contract will be void if you do not sign it within one month.
Remember to get started with your connection in good time; it may take as long as several months to determine the price for a site that requires extensive preliminary investigation. This work may include connections outside the zonal model or situations in which the network needs to be reinforced over a long distance.
Precise descriptions of the zonal pricing model
Zone 1 | Areas with a city plan and connections with a directly measured distance from an existing secondary substation of up to 300 metres. In shore plan areas, the zone pricing is based on distance. |
---|---|
Zone 2 | Connections with a directly measured distance from an existing secondary substation from 300–600 metres. |
Zone 3 | Connections with a directly measured distance from an existing secondary substation from 600–800 metres. Main fuse size max. 3x35 A. |
Area outside the zones | Area or case-specific pricing, where the connection fee consists of direct network expansion costs and a capacity reservation fee. |

Pricing of medium voltage connections
Medium voltage connections are priced on a case-by-case basis. The connection fees for medium voltage connections consist of the direct network expansion costs and a capacity reservation fee.
We will determine the price of the medium voltage connection when you send us the details of the medium voltage connection via the connection order pathway.
Price lists