Non-standard-priced connection outside the zonal model

The prices of electricity connections are determined by a so-called zonal pricing model. If your connection point is outside Caruna's zonal model for electricity connections, the connection charge consists of the actual network construction costs.

The connection zone is determined according to the distance to the nearest secondary substation, as well as the size of the main fuse for the connection. Outside the zonal model, the connection charge consists of the actual costs of building the medium and low voltage network. In addition to network construction costs, a capacity reservation fee is added to the connection charge. In our planning, we use your quote request to determine the price of a connection outside the zonal model.

We’ll process your quote request either on a regional or on a case-specific basis, depending on whether there are other possible connection points nearby. In order to determine the type of execution, we carry out an analysis of the area in connection with the quote request. In the analysis, we will review any other possible connection points in the area which could be connected to a new transformer circuit or distribution network branch at the same time. This enables the most affordable connection charge, as well as an opportunity for everyone interested to join the electricity network. The potential connecting parties may be building sites in the town plan, existing buildings and sites with exemption permits. 

Find out the indicative price estimate for constructing the medium voltage network required for the connection and submit a quote request if you wish. We will plan the construction of the medium and low voltage network based on your quote request and contact you regarding the connection charge and delivery time.

Request a quote

Execution outside the zonal model

Connection with regional pricing

1. Find out the price and request a quote

Find out the indicative price estimate for the construction costs of the medium voltage network in the area and submit a quote request for the connection charge.

The quote should be requested in good time. It takes time to estimate the price and delivery time, and to analyse the area. Connections outside the zones typically require extensive construction of the electricity network. It is good to prepare for a long waiting time from ordering the connection to being able to use the electricity.

Read more and request a quote

2. We analyse the area based on your quote request

During the quoting process, we will find out how many potential connection points in the area that are located at an appropriate distance and define the area based on the locations of potential connection points.

3. We plan the construction of the electricity network in the area

We plan the construction of the electricity network for your connection as cost-effectively as possible, for example, in terms of the chosen route and terrain conditions. The planning is based on the assumption that the connection size is 3x25 A. Larger connections are considered specific cases.

The connection charge consists of the extension of the medium and low voltage network to be constructed for new connections, as well as a connection-specific capacity reservation fee. Construction costs are divided between new connecting parties in the area. There is no charge for strengthening a pre-existing network.

4. We start a bidding round

Once the regional connection charge has been determined, we will confirm your interest in starting a bidding round. If you are still interested, we will send the real estate owners of potential connection points in the area a written quote regarding interest in ordering an electricity connection with a regional connection charge. The quote is valid for one month.

5. The results of the bidding round arrive

We will announce the result of our survey to those interested in acquiring a connection. In order for the area project to be executed, the connection charges must cover at least 60% of the costs for building the electricity network in the area. The minimum number of connections is case-specific and is shown in the quote that we will send to potential connecting parties in the area.

If there are less interested parties than the minimum number of connections, we can calculate a new quote price for interested parties, where a smaller number of connecting parties take on the construction costs for the area to be electrified.

6. Signing the connection contracts

If there are enough interested parties, we will send the interested parties connection contracts to sign. In the connection contract, we confirm the price of the connection, the delivery time and the connection point. The delivery time defined in the connection contract begins when Caruna gains the necessary land use rights for the network, with standard terms. Network construction will be implemented in the area if all interested parties return their signed connection contract by the deadline.

7. Network construction

We will start building the network in the area when the required number of signed connection contracts have been returned. At this stage, we will determine the exact type of execution for constructing each connection in the terrain. Our contractor will contact the area’s connecting parties about the implementation and construction schedule.

The delivery time defined in the connection contract begins when Caruna gains the necessary land use rights for the network, with standard terms.

8. Conclude an electricity contract with an electricity supplier

In addition to the connection contract, you should conclude an electricity contract with an electricity supplier. Activating the connection requires an electricity contract, so contact your electricity supplier in good time. Invoicing of the electricity contract will only start when the connection has been activated for you.

9. Your electricity contractor submits a general request form on the activation of the connection

Your electricity contractor is responsible for electrical installations within your real estate from the connection point indicated in the connection contract. They purchase and install the main exchange and connection cable for your connection and order the activation of the connection using the general request form. The general request form must be sent to Caruna in good time, no later than three weeks before the desired connecting date.

10. We will activate the connection for you

We can activate the connection when the connection contract has been signed, potential network construction has been completed, the general request form has been received, and the electricity contract has been concluded. Once your connection is activated, you will get access to our electronic self-service channel Caruna+. In the service, you can view your electricity consumption, browse or update your customer information, and pay your invoices.

Case-specific connection

1. Find out the price and request a quote

Find out the indicative price estimate for the construction costs of the medium-voltage network for the connection and submit a quote request for the connection charge.

The quote should be requested in good time. It takes time to estimate the price and delivery time, and to analyse the area. Connections outside the zones also usually require extensive construction of the electricity network. It is good to prepare for a long waiting time from ordering the connection to being able to use the electricity.

Read more and request a quote

2. We analyse the area based on your quote request

We will verify if there are other potential connection points in the area. If there are no other potential sites for electrification near your connection point, the connection is implemented as a case-specific order.

3. We plan the construction of an electricity network for your connection

When we have established that your connection i case-specific, we plan the construction of an electricity network for your connection as cost-effectively as possible, for example, in terms of the chosen route and terrain conditions.

The connection charge consists of the extension of the medium and low voltage network to be constructed for your connection, as well as a capacity reservation fee, which is based on the size of the connection. There is no charge for strengthening a pre-existing network.

It may be possible to implement a single connection without building a medium voltage network, but a low voltage network must always be built. An existing electricity network near your future connection may lower the amount of your connection charge.

4. The price and delivery time of the connection are confirmed

We will contact you about the price of the connection according to the requirements of your quote request. If you wish to proceed with implementing the connection at the quoted price, we will send you the connection contract to sign.

5. Sign the connection contract

In the connection contract, we confirm the price of the connection, the delivery time and the connection point. The delivery time defined in the connection contract begins when Caruna gains the necessary land use rights for the network, with standard terms.

6. Network construction

We will start network construction for your connection when we have received your signed connection contract. At this stage, we will determine the exact type of execution for constructing the network in the terrain. Our contractor will contact you about the implementation and construction schedule.

The delivery time defined in the connection contract begins when Caruna gains the necessary land use rights for the network, with standard terms.

7. Conclude an electricity contract with an electricity supplier

In addition to the connection contract, you should conclude an electricity contract with an electricity supplier. Activating the connection requires an electricity contract, so contact your electricity supplier in good time. Invoicing of the electricity contract will only start when the connection has been activated for you.

8. Your electricity contractor submits a general request form on the activation of the connection

Your electricity contractor is responsible for electrical installations within your real estate from the connection point indicated in the connection contract. They purchase and install the main exchange and connection cable for your connection and order the activation of the connection using the general request form. The general request form must be sent to Caruna in good time, no later than three weeks before the desired connecting date.

9. We will activate the connection for you

We can activate the connection when the connection contract has been signed, potential network construction has been completed, the general request form has been received, and the electricity contract has been concluded. Once your connection is activated, you will get access to our electronic self-service channel Caruna+. In the service, you can view your electricity consumption, browse or update your customer information, and pay your invoices.

Questions and answers

Can I lower the connection charge if more people order a connection at the same time?

With regional pricing, the connection charge consists of the construction costs for the medium and low voltage network as well as a capacity reservation fee. If there are several potential connection points in the area, construction costs will be split amongst the connecting parties. We will define the area and potential connection points when processing your quote request.

Is it my responsibility to find out if my neighbors are interested in acquiring a connection?

Caruna is responsible for defining the area and mapping potential buyers. If you wish, you can also talk to the neighbours and, for example, mention other interested parties in your quote request.

How can I let you know that my neighbor is interested in an electricity connection as well?

You can tell us about other known interested parties in the Further information field of the quote request. If you have already sent a quote request, please contact us in the chat and mention the transaction number of your quote in the chat.

Do I commit to purchasing an electricity connection if I fill in a quote request?

No. First, check your indicative price estimate on the connection pathway. If you are interested in a more accurate price, please send us a quote request. We will contact you about the quote. In the case of a connection with regional pricing, we will send the quote by mail both to you and to the landowners. If there is enough interested people in the area, we will send binding connection contracts to sign. In the case of a single connection with case-specific pricing, we will contact you about the quote before sending connection contracts.

Can I influence the construction plan myself? For example, with regard to the cable route.

If the project is initiated and there is enough interest, our designers will discuss the network construction plan with the landowners. We strive to take special requests into account, if possible.

Will the price change if there are changes to the network construction plan?

The regional price indicated in the signed connection contract is binding throughout the period of validity of the area, even if there are changes to the network construction plan.

Will I get a refund for my connection charge if other connecting parties move in to the same area at a later date?

The special terms of the connection contract contain a subsequent connecting party clause, hence, refund will be paid in accordance with Caruna's connection principles.

How long does it take to map the price of a connection or other interested parties in the area?

In principle, it is a good idea to reserve approximately 1 to 3 months for the processing of your quote request. In cases with regional pricing, mapping interested parties and sending quotes by mail already takes about a month.

When is the connection charge invoiced?

The connection will be invoiced when network construction has been completed and the connection can be connected to the network.